Welcome to the 4-8 Middle School Construction Project |
Please contact the School Building Committee at easthaddamsbc@yahoo.com with any questions or comments. The public is encouraged to attend the Committee's meetings, held on the second and fourth Wednesday of the month at 7 p.m. in the Media Center at Nathan Hale-Ray High School. |
February 2007 – Excavation begins after residents approve allocating extra funds at January 25th referendum.
|
|
April 2007 - DeRita Construction, the site construction contractor, is near completion with site clearing. |
||
![]() |
![]() |
![]() |
May, 2007: Storm drainage pipes are installed throughout the site. |
May, 2007: The site’s electrical conduits are installed underground at the two-story classroom wing, which will house the 6th through 8th grades. |
May, 2007: The main access driveway from Clark Gates Road has been cut in and should have the first course of pavement by July 1st. |
![]() |
![]() |
May, 2007: Foundation work is underway and near completion at two of the five building “wings”. |
|
![]() |
![]() |
![]() |
Structural Steel formation has begun! |
||
During the summer months, the foundations for the entire school are nearly complete while the structural steel will be completed in mid-October.
|
|
![]() |
![]() |
The front entrance of the school |
The 2-story classroom wing which will house 6th-8th graders |
October 2007 |
||
![]() |
![]() |
![]() |
Soccer Field |
Administration & Entry Ways |
4 -5 Wing |
![]() |
![]() |
![]() |
4 - 5 Wing |
6 - 8 (front view) |
6 - 8 Wing |
![]() |
![]() |
![]() |
6 - 8 Wing (side view) |
6 - 8 (rear view) |
Media Center & 6 - 8 Wing (rear view) |
![]() |
![]() |
![]() |
Gynmasium |
Art Room |
Gymnasium |
![]() |
![]() |
![]() |
Art Room |
Media Center |
Stairs Near Administration |
![]() |
![]() |
![]() |
6 - 8 Wing Hallway |
Classroom 6 - 8 Wing |
Topping Off Ceremony |
![]() |
||
February 2008 |
||
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
|